Construction in August 2026: work completed during the month

Throughout August, a continuous construction process was underway across key Perfect Group sites. The team actively kept working according to plan, adapting to any weather or safety conditions.

Read more

Stanford RC

Section 101 

  • Active installation of double-glazed units and stained-glass window structures
  • Facade insulation and preparation for porcelain stoneware installation ongoing
  • Completed 200 m³ of brickwork
  • Installed 1st roofing layer and wet facade
  • Completed preparations for floor tiling in common areas
  • Routing of vertical risers for water supply, sewerage, and stormwater drainage

Section 102 

  • Completed floor tiling in common areas
  • Finishing works on the ventilated facade
  • Doors installed in common areas
  • Fire protection and alarm systems installed

Section 103 

  • Installation of a wet facade on the roof
  • Rooftop boiler house assembly ongoing
  • Routing of vertical risers for water supply, sewerage, and stormwater drainage

Sections 106-107

  • Concreting of entrance group elements ongoing

Section 109 

  • Completed the monolithic frame of residential floors
  • Poured 43 m³ of concrete

Section 110

  • Monolithic works ongoing on floor -1
  • Poured 50 m³ of concrete

Parking 

  • Completed the floor slab over floor -1
  • Installation of parapets and entrance groups ongoing
  • Poured 120 m³ of concrete and completed 100 m³ of brickwork

Additionally, laying of the stormwater sewer across Yevhena Konovaltsia Street is in progress.

Apart-hotel VELMY

Block А

  • Completed vertical elements of the 5th floor; concreting of the floor slab is 70% complete
  • Completed interior brickwork and partition walls from floors 1 to 3; 4th floor is at 90%
  • Completed installation of aluminum window and door units for terrace access on floors 1–3; 4th floor is at 90%

Block В

  • Completed vertical elements and floor slabs for floors 3–5; rebar cages for the 5th-floor vertical elements are fully ready
  • Interior brickwork on the 2nd floor is 22% complete

Stilobate between Blocks A and B

  • Preparation of pile heads under the stilobate retaining wall is fully complete
  • Installed drainage wells under the stilobate (4 units)
  • Completed the walls of the stilobate transition tunnel

Phase 2

  • Soil excavation from the Block E pit is 90% complete; Block D pit is at 80%
  • Installation of tension anchors for the retaining wall: second tier — 100%, third tier — 30%
  • Crushed stone backfilling along axis P is 90% complete

Clubhouse La Manche

Section 1

  • Completed apartment-level installation of water and heating supply pipes, as well as cement-sand floor screed from floors 2 to 7
  • Completed floor screed in the transformer substation at the -3.900 level (floor -1)

Section 2

  • Completed apartment-level installation of water and heating supply pipes from floors 2 to 7
  • Cement-sand floor screeding has commenced

Section 3

  • Installed apartment entrance doors, as well as technical doors and concealed access hatches from floors 2 to 8

Section 4

  • Insulation of balcony undersides with 100 mm mineral wool ongoing from floors 3 to 9
  • Insulation of balcony edges with 100 mm polystyrene ongoing
  • Completed balcony waterproofing and installed stormwater drainage funnels from floors 2 to 8

Section 5

  • Completed installation of decorative elements around door and balcony units, as well as decorative plastering and painting of balcony undersides from floors 3 to 8

New Tone RC

Residential Building 1

  • Section 1.1 – 6th-floor slab poured; aerated concrete blockwork ongoing
  • Section 1.2 – Roof slab completed

Residential Building 2 

  • Section 2.2 – Blinding concrete preparation and waterproofing under the foundation slab in progress
  • Sections 2.3 – 2.5 – Concreting of 1st-floor vertical elements in progress
  • Section 2.6 – Foundation slab poured; concreting of basement vertical elements in progress
  • Section 2.7 – Blinding concrete preparation under the foundation slab and elevator pit ongoing

Additionally, another tower crane has been assembled near Section 2.1. Soil backfilling has been completed in the area of Sections 2.3–2.5, and a new tower crane has also been installed there.

Polaris Home&Plaza PC

Section 4.1

  • Radiators purchased for floors 3–26; installation completed on floors 24–26
  • Frame and perimeter seals assembled for 1st-floor translucent facade structures — 108 m²
  • Aluminum window and door structures manufactured for the 2nd floor — 114 m²; delivered to the site
  • Pre-plastering preparation completed on floors 1–2
  • Lighting installed in cold passages and stairwells
  • Applied decorative plaster and painted 100 m² of the facade

Section 3.3

  • 40 m² of facade insulated, with decorative plaster applied and painted over the same area

Section 3.2

  • Fire suppression risers installed from floors 3 to 26
  • Facade insulation and reinforcement completed over 850 m²; 500 m² of decorative plaster applied, and 200 m² painted

Section 3.1

  • Wall and partition masonry ongoing on the 26th floor
  • Window installation completed up to the 25th floor
  • Preparations for roofing works ongoing
  • Insulation and adhesive-mesh reinforcement completed for ventilation ducts and parapets
  • Heating, ventilation, water supply, and sewerage piping routed from floors 5 to 16
  • Electrical wiring for pre-plastering works completed from floors 5 to 23
  • 3,250 m² of facade insulated, and 2,150 m² reinforced

Section 2.2

  • Wall and partition masonry completed on floors 4–9; works ongoing on floors 10 to 15
  • Ventilation blocks installed up to the 26th floor; flight stairs installed up to the 21st floor

Parking D

  • Vertical elements of the 2nd floor and part of the slab over the 2nd floor completed
  • Vertical waterproofing of the parking structure in progress

Transformer Substation No. 2

  • Completed slab over the 1st floor and walls of the 2nd floor

Transformer Substation No. 1

  • Foundation completed

A total of 653 m³ of concrete was poured at the site between August 1 and August 31.

Always get the news on time!

Receive the latest news, helpful tips, and special offers straight to your inbox

Please enter your name

Please enter a valid email address

Still have questions?

  • Want to calculate the cost of an apartment?
  • Want to see everything with your own eyes?
  • Want to learn more about the programs?
Book a consultation