Construction in June 2026: work completed during the month

June 2026 also proved to be quite productive for Perfect Group's projects. Work on the active construction sites never ceased, with builders working hard both on the exteriors and inside the properties.

Read more

Stanford RC

Section 101

  • 250 m³ of brick masonry completed
  • shaping of arched window openings and steel reinforcement is ongoing

Section 102

  • 20 m³ of brick masonry completed
  • installation of window systems is nearing completion
  • utility installation (sewerage, water supply, and heating) is in its final stage
  • façade works on the courtyard side are nearing completion
  • floor screeds have been completed, with tiling of the stairwells scheduled next

Section 103

  • 50 m³ of brick masonry completed
  • installation of window systems has begun

 Section 109

  • active structural concrete works continue, with the 8th residential floor 50% complete

Parking

  • concreting of the floor slab above Level -1 is 50% complete
  • 116.8 m³ of concrete delivered

Apart hotel VELMY

Block A

  • Level 4 floor slab concreting — 100%
  • Level 5: vertical structural elements — 80%, horizontal slab formwork — 90%, floor slab — 80%
  • internal and external ceramic block masonry on Level 2 completed
  • brick masonry of internal walls and partitions on Level 3 — 80%
  • aluminium terrace window and door systems completed on Level 1; Level 2 installation — 80%

Block B

  • vertical structural elements and floor slab concreting for Levels 3–4 — 100%
  • reinforcement cages for Level 5 vertical elements — 20%
  • internal wall masonry on Level 1 completed

Podium between Blocks A and B

  • pile trimming to design level, excavation, and soil removal for the connecting tunnel completed

Phase 2

  • installation and tensioning of retaining wall anchors (Level 1) — 100%
  • excavation spoil removal: Block E — 70%, Block D — 10%
  • retaining wall anchor installation (Level 2) — 10%

Clubhouse La Manche

Section 1

  • electrical network installation completed in common areas and stairwells from Levels 10 to 1

Section 2

  • electrical network installation completed in common areas
  • plastering completed in common areas from Levels 10 to 3

Section 3

  • plastering completed in common areas and stairwells
  • water supply and heating pipelines installed from Levels 10 to 2

Parking

  • formwork installed and Ø100 mm corrugated cable mounted in the electrical room on Level -1

Façade

  • installation of porcelain stoneware cladding and decorative elements is ongoing
  • balcony waterproofing on the Shchekavytska Street side and installation of roof drainage outlets are in progress

New Tone RC

Residential Building 1

  • Section 1.1 — Level 4 floor slab completed
  • Section 1.2 — masonry works continue, with significant progress on Levels 2–3
  • backfilling has begun on the Estonska Street side for both sections

Residential Building 2

  • Sections 2.3–2.4 — partial concreting of the basement vertical structural elements completed
  • Section 2.5 — concrete blinding completed for the foundation slab

Polaris Home&Plaza RC

Section 4.1
Façade: insulation — 220.00 m², reinforcement — 413.41 m², decorative plaster — 770.00 m², painting — 1,075.00 m².

Section 3.3
Façade: insulation — 23.06 m², reinforcement — 90.00 m², decorative plaster — 950.00 m², painting — 1,280.00 m².

  • water supply and heating manifolds installed
  • shut-off valves installed for apartment water supply and heating systems
  • control valves installed for the fire protection system
  • cable tray installation started on Floors 1–2
  • “American” wall plastering completed on Floors 3–26
  • waterproofing of cold transition areas completed on Floors 3–26
  • tiling completed on Floors 18–26

Section 3.2
Façade: insulation — 1,450.00 m², reinforcement — 2,350.00 m², decorative plaster — 1,750.00 m², painting — 1,200.00 m².

  • heating and water supply pipelines installed on Floors 3–26
  • sewer risers completed on Floors 3–12
  • water supply risers completed on Floors 3–10
  • apartment utility conduits installed on Floors 4–17
  • cement-sand screed completed on Floors 8–18

Section 3.1

  • masonry completed on Floors 14–19 and 21–23
  • masonry started on Floors 25–26
  • roof shaft masonry is nearing completion
  • window installation completed up to Floor 16
  • roofing works have begun
  • roofing felt vapour barrier completed to approximately 70%

Section 2.2

  • structural concrete works for the vertical elements of Floor 25 completed
  • floor slab above Floor 25 is 50% complete

Section 2.1

  • vertical elements of Floor 4 completed
  • floor slab above Floor 4 completed

Parking D

  • concreting of vertical structural elements has begun

Transformer Substation No. 2

  • excavation completed
  • concrete blinding completed

Podium (Section 3.2)

  • excavation works have begun

A total of 1,230 m³ of concrete was used on site in June.

Always get the news on time!

Receive the latest news, helpful tips, and special offers straight to your inbox

Please enter your name

Please enter a valid email address

Still have questions?

  • Want to calculate the cost of an apartment?
  • Want to see everything with your own eyes?
  • Want to learn more about the programs?
Book a consultation