04.06.2026

Construction in May 2026: work completed during the month

May 2026 became yet another productive period for the company. Over the course of this month, a significant volume of construction processes was successfully completed across five active Perfect Group project sites.

Read more

Stanford RC

Section 101 

  • Installation of window structures is ongoing.

Section 102 

  • In progress: routing of heating and water supply systems across apartments and installation of floor screed.
  • In the final stages: facade work on the inner courtyard side.

Section 103 

  • Routing of heating and water supply systems across apartments and installation of floor screed are ongoing.
  • Insulation of parapets and ventilation shafts is underway.

Section 106 

  • Facade work on the basement floor facing the inner courtyard is nearing completion.
  • In the final stages: installation of fire protection systems.

Section 109 

  • The monolithic structure of the 5th residential floor has been completed, and construction of the 6th-floor vertical elements is underway.
  • 218.1 m³ of concrete were poured.

Parking 

  • The floor slab over the -2 floor has been completed, and work on the construction of the -1 floor is ongoing.
  • 379.8 m³ of concrete were poured.

Apart-hotel VELMY

Block А

  • Concreting of the 4th-floor slab has been completed.
  • Vertical structures of the 5th floor are 40% complete.
  • Setting up the horizontal shuttering for the 5th-floor slab is 25% complete.
  • Laying of external and internal walls made of ceramic blocks on the 3rd floor is 100% complete.
  • Laying of internal walls and partitions made of solid clay bricks on the 3rd floor is 25% complete.
  • Installation of aluminum window and door units for the 1st-floor terrace access is 100% complete, and 10% complete on the 2nd floor.

Block В

  • Vertical structures and concreting of the 3rd-floor slab have been completed.
  • Vertical structures of the 4th floor are 45% complete.
  • Setting up the horizontal shuttering for the 4th-floor slab is 20% complete.
  • Laying of internal walls on the 1st floor has been completed.

Stylobate between blocks A and B

  • Trimming of piles to the design horizontal level is 15% complete.
  • Excavation and removal of soil from the transition tunnel between blocks A and B are 85% complete.

Phase 2

  • Installation and tensioning of tieback anchors on the 1st tier of the retaining wall are 100% complete.
  • Soil excavation and removal from the Block E pit are 5% complete.

La Manche Clubhouse

Section 4

  • Technical flush-mount doors have been installed from the 2nd to the 8th floor; apartment doors from the 2nd to the 4th floor.
  • Drilling of holes in the balcony concrete for waterproofing and rainwater drainage funnels is underway.

Section 5

  • Apartment doors have been installed up to the 8th floor.

Section 3

  • Installation of Gemafon from the 2nd to the 10th floor for the subsequent routing of water and heating supply networks is underway.

Section 2 

  • Installation of electrical grids in common areas for lighting has been completed.

Section 1 

  • Work has commenced on the installation of electrical grids in common areas.

Polaris Home&Plaza RC

Section 4.1 

  • Facade insulation has been completed — 110 m². Decorative plaster has been applied — 4,750 m². The facade has been painted — 700 m².
  • Tiling of floors in common areas has been completed from the 3rd to the 11th floor.
  • Work is ongoing on the installation of the decorative layer for walls and ceilings.

Section 3.3 

  • Facade insulation has been completed — 150 m². Facade reinforcement — 250 m². Application of decorative plaster — 450 m². Facade painting — 275 m².
  • Plastering of common area walls from the 3rd to the 11th floor has been completed.
  • Installation of apartment and technical doors from the 3rd to the 26th floor is 90% complete.

Section 3.2 

  • Facade insulation has been completed — 500 m². Facade reinforcement — 400 m². Application of decorative plaster — 700 m². Facade painting — 400 m².
  • Plastering of common area walls from the 3rd to the 12th floor has been completed.
  • Floor screed installation from the 18th to the 23rd floor has been carried out.
  • Installation of heating and water supply pipes from the 3rd to the 18th floor is ongoing.

Section 3.1 

  • Brickwork of the 20th floor has been completed. Brickwork continues on the 14th, 15th, 17th, 21st, and 22nd floors. Work has commenced on the 23rd floor.
  • Window installation from the 9th to the 13th floor has been completed.

Section 2.2 

  • Installation of the floor slab over the 21st floor and vertical structures of this level has been completed.

Section 2.1 

  • Vertical structures of the elevator and stair core on the 3rd floor are complete.
  • Reinforcement of the elevator and stair core floor slab over the 3rd floor is 60% complete.

Parking

  • Installation of the concrete bedding and monolithic foundation works have been completed.

In total, between May 1 and May 31, 2,429.5 m³ of concrete were poured at the site.

New Tone RC

Section 1.1

  • The 3rd-floor floor slab and vertical structures are complete.
  • Reinforcement of the 4th-floor floor slab has commenced.

Section 1.2

  • 10 flights of stairs have been installed.

Section 2.3

  • Reinforcement and concreting of basement walls and vertical structures are partially complete.

In addition, the arch covering for sections 1.1 – 2.3 has been completed. Over the past month, 264 m³ of concrete were poured at the site.

Always get the news on time!

Receive the latest news, helpful tips, and special offers straight to your inbox

Please enter your name

Please enter a valid email address

Still have questions?

  • Want to calculate the cost of an apartment?
  • Want to see everything with your own eyes?
  • Want to learn more about the programs?
Book a consultation