Stanford RC
Section 101
- installation of window structures continues
- 140 m³ of brickwork completed
Section 102
- the facade on typical floors facing the inner courtyard is in its final stages
- 20 m³ of brickwork completed
Section 103
- distribution of water supply and heating networks across apartments is ongoing
- laying of floor conduits for subsequent apartment power cable installation continues
- installation of cement-sand floor screed is in progress
- 40 m³ of brickwork completed
Section 106
- facade work has commenced on the lower floors facing the inner courtyard
Section 109
- the floor slab above the 2nd residential floor and vertical elements of the 3rd floor are completed
- formwork assembly for the floor slab above the 3rd residential floor has commenced
- 179 m³ of concrete poured
Parking
- vertical elements of the -2 level are completed and floor slab installation over the -2 level has commenced
- 154 m³ of concrete poured
Additionally, insulation works on parapets, partitions, boiler room walls, and ventilation shafts using the wet facade technique are ongoing on the roof of sections 102-103.
Works on the boiler room of section 106 are nearing completion, and preparatory activities for the boiler room of section 103 have commenced.


Apart-hotel VELMY
Block А
- formwork for the 4th-floor slab is 50% complete
- reinforcement cage for the 4th-floor slab is 90% complete
- masonry for internal and external walls of the 1st and 2nd floors is finished
- internal wall masonry on the 3rd floor is 20% complete
Block В
- vertical elements of the 3rd floor are 95% complete
- formwork installation and reinforcement for the 3rd-floor slab are 90% complete
- internal wall masonry on the 1st floor is finished
Stage 2
- tension anchors for the 1st tier retaining wall are 90% complete
Additionally, the pile field for the stylobate of blocks A and B is 100% complete


La Manche Clubhouse
Section 4
- cement-sand floor screed is completed from the 2nd to the 10th floor
- installation of decorative elements around the windows has commenced
Section 5
- technical concealed doors have been installed from the 2nd to the 8th floor
- apartment entrance doors are installed from the 2nd to the 3rd floor
- plastering and painting of window reveals are ongoing
- installation of porcelain stoneware tiles on balconies is in progress
- a portion of the decorative window elements and ACP (aluminum composite panel) partition cappings have been completed


Polaris Home&Plaza RC
Section 4.1
- 450 m² of facade insulation, 1,710 m² of facade reinforcement, 1,500 m² of decorative plastering, and 235 m² of facade painting have been completed
- wall finishing in common areas from the 3rd to the 26th floor and floor tiling in common areas from the 11th to the 26th floor are completed
Section 3.3
- 1,020 m² of facade insulation, 1,700 m² of reinforcement, 780 m² of decorative plastering, and 600 m² of painting have been completed
- wall plastering in common areas from the 12th to the 26th floor is completed
- installation of water supply manifolds, shut-off and control valves for heating and water risers, and installation of heating outlets in the elevator zone have been carried out
Section 3.2
- 2,080 m² of facade insulation, 3,035 m² of reinforcement, and 750 m² of decorative plastering have been completed
- wall plastering in common areas from the 12th to the 26th floor and installation of floor screed from the 24th to the 26th floor are completed
- cable routing on floors 4 through 9, installation of floor conduits from the 4th to the 26th floor, and installation of heating and water supply pipes on floors 18 through 26 have been carried out
Section 3.1
- masonry for the 13th, 16th, 18th, and 19th floors is finished; work continues on the 14th, 15th, 17th, 20th, 21st, and 22nd floors
- installation of the floor slab above the 26th floor is completed, and work on the monolithic parapet has commenced
Section 2.2
- installation of the floor slab above the 19th floor and the vertical elements of this level is completed; vertical elements of the 20th floor are also finished. Currently, work on the floor slab above the 20th floor is in progress.
Section 2.1
- vertical elements of the lift and stair core on the 2nd floor are completed, and reinforcement of the core’s floor slab above the 2nd floor is finished
Parking
- excavation of the foundation pit is approximately 90% complete, and the installation of crushed stone and lean concrete bedding is approximately 60% complete
A total of 880 m³ of concrete was poured over the month.


New Tone RC
Section 1.1
- concreting of the 2nd part of the 3rd-floor structural core is completed
- installation of the reinforcement cage for the 3rd-floor slab is in progress
Section 1.2
- concreting of the 7th-floor slab is completed
- concreting of the 8th-floor vertical elements is completed
Scaffolding and formwork for the arch between sections 1.1 and 2.3 have been installed; the reinforcement cage for the arch covering is currently being mounted.
A total of 121.8 m³ of concrete was placed on-site during the month of April.