Monolithic works are 100% complete in sections 101, 102, and 111.
Construction of all residential floors in section 108 has been finalized.
The underground parking garage is 100% complete at level -5 and 75% complete at level -4.
In total, 8,523 m³ of concrete was poured at the site over the year, with the highest volume recorded at section 101 (2,128 cubic meters).
2,450 m³ of brick masonry was completed.
-
Over the year, a range of works was fully completed in sections 104 and 106:
-
Floor screed and wall plastering in common areas — 100%
-
Installation of heating and water supply pipes in apartments — 100%
-
Routing of electrical wiring in common areas and fire safety systems — 100%
-
-
In section 102:
-
The insulated facade system has been 100% completed on typical floors facing Ye. Konovaltsia Street.
-
Elevators have been installed.
-
Roofing works have been fully completed.
-
Additionally, the roofing of section 103 is 100% ready.
Insulation and the facade system of section 104 have also been completely finished. The exterior landscaping of this section is 100% complete as well.
100% of apartment doors and common area doors have been installed in sections 104 and 105.
In section 106, insulation and the installation of the clinker facade on typical floors have been fully finalized.
Installation of external utility networks (water supply, sewage, and stormwater drainage for the inner courtyard driveway) has been completed, including connections to the municipal grid.
A transformer substation has been installed to supply power to the residential complex, and commissioning works for its connection to the city grid have been successfully carried out.