Construction in November 2025: work completed per month

During November 2025, a significant amount of work was completed at all company sites.

Read more

Stanford Residental Complex

Section 101
– 2 floors of brickwork completed
– 30% of parapets and complex-shaped technical rooms completed

Section 102
– 95% of facade works from the side of Ye. Konovaletsa Street on typical floors are completed
– fully assembled guide elements and elevator cabins, installation of exit doors and commissioning work are underway
– protective layers of the roof of sections 102 and 103 are completed, finishing works are underway

Section 106
– boiler room is 80% ready,  ITP and pump room are 99% ready
– installation of clinker facade elements is underway
– installation of the subsystem for facing the first floors with porcelain stoneware is underway.

Section 110
– work is being completed on the -1st floor from the side of Predslavynska Street (-2 from the side of the courtyard)

Parking
– 20-25% of the total volume of the fifth enclosure has been completed
– 50% of the floor slabs of the -5 and -4 floors are ready
– on the -5 floor, vertical elements for the installation of entry and exit ramps (“snails”) have been completed.
230 m³ of concrete was received per month. 150 m³ of brickwork was completed.

Polaris Home&Plaza Residental Complex

Sections 4.1–3.3
– Wall decoration and door installation in technical rooms have been completed.
– Floor tiling is in progress.

Section 3.2
– Window structures are being installed on the 24th floor.

Section 3.1
– Monolithic works: vertical elements and floor slab above the 25th floor have been completed.
– Masonry works on the walls of the 8th and 9th floors have been completed.
– Masonry works on the walls of the 10th and 11th floors are in progress.

Section 2.2
– Monolithic works: vertical elements and floor slabs above 6-7 floors completed.
– Vertical elements of the 8th floor completed.
– Arrangement of the floor slab above the 8th floor is in progress.

A total of 742.6 m³ of concrete was received per month.

Apart hotel VELMY

Block А

  • Vertical structures (columns, ventilation units, pylons, external and internal walls) of the 3rd floor are 50% complete.
  • The formwork of the 3rd floor floor slab is 50% complete.

Block B

  • Vertical elements of the 2nd floor are 100% complete
  • Formwork of the 2nd floor floor slab is 70% complete
  • Concreting of the 2nd floor slab is 20% complete
  • Vertical and horizontal waterproofing is completed and 85% backfilling with crushed stone with layer-by-layer tamping is completed
  • Drainage is 100% complete
  • Concreting is performed in compliance with the requirements of electric heating of concrete in the winter period.

La Manche Clubhouse

Section 4
– electrical networks for lighting public areas and corridors from floors 2 to 10 were laid
– plastering of walls from floors 2 to 10 was carried out
– arrangement of electrical panels and installation of metal structures for connecting cables beganв

Section 5
– cement-sand screed from floors 2 to 10 completed