13.02.2026

Construction in January 2026: work completed per month

2026 has started at the sites of Perfect Group facilities. Unfortunately, enemy shelling, energy problems, and weather conditions have somewhat slowed down the pace of work. But work continues every day. During January, the following was completed:

Read more

Stanford Residential complex 

Section 101
– bricklaying of external and internal walls is underway – 20 m3 have been completed per month

Section 103 
– laying of heating pipes and external sewage

Section 106 
– work on the ventilated facade is being completed – installation of frames and insulation of the first floors is underway
– the boiler room is 98% ready. The hydraulic pump and the gas supply system for the boiler room have been installed
– the boilers have been wired

Section 109 
– 30% of the vertical structures of the 1st floor are completed. Reinforcement frames are 90% ready
– 22 m3 of concrete have been received

Section 110 
– preparation of reinforcement structures continues
– inlets for domestic sewage installed

In addition, the storm sewer system has been installed and the entire facility has been connected to the city network. Preparation of reinforcing structures for the execution of vertical elements of the -4th floor of the parking lot is underway.

Apart-hotel VELMY

Block А 
– 70% concreting of the floor slab at -3.3 has been completed
– waterproofing works are in progress. From -12 to -3.3 100% readiness. From -3.3 to 0 – in progress

Block B 
– floor slab at -3.3 is 100% complete
– installation of reinforcement cages for vertical elements at -3.3 is 100% complete
– horizontal formwork elements at 0.0 are 20% complete

Polaris Home&Plaza Residental complex

Section 4.1
– Installation of mineral wool on the facade, installation of brackets for air conditioner baskets.
– Installation of water supply and heating systems.

Section 3.3
– Installation of mineral wool on the facade, installation of brackets for air conditioner baskets.
– Installation of equipment for boiler room No. 1 and IHTP No. 1.

Section 3.2
– Laying in the area of ​​cold transitions.

Section 3.1 
– Work on installing window structures on floors 5, 6 and 7 has been completed.
– Wall construction continues on floors 11 and 12.
– Installation of ventilation units is underway – 23 floors have been installed, installation of reinforced concrete stairs – 16 floors have been installed

Section 2.2 
– Ventilation units are being installed – 3 floors have been installed.

La Manche Clubhouse 

Facility readiness as of February 2026:

Sections 6 and 7: Facade work has been fully completed and entrance doors to the apartments have been installed.

Sections 5, 6, 7: Elevators have been installed. Cement-sand screed has also been installed on the floors in the apartments (from floors 2 to 10).

Sections 4, 5, 6, 7: The electrical networks and gypsum plaster in the MZK are 100% complete. Water supply is distributed to the apartments (2–10 floors).

All sections (1–7): Window structures are 100% installed.

Facade work is currently underway on sections 4 and 5 – insulation and installation of porcelain stoneware are underway.

The active phase of construction will start in the spring, when warming will allow work that requires compliance with temperature regimes to be carried out.