Apart-hotel VELMY
Block А
– 50% of the floor slab at the level of -3.3 is filled
– the installation of the frames of the vertical elements from the level of -6.6 to the level of -3.3 is in progress
– waterproofing works are in progress on the side of the retaining wall
– preparation for the masonry of the external walls made of ceramic blocks and the internal walls made of solid brick on the 1st floor is in progress
Block B
– installation of frames and formwork from level -3.3 to level 0.0 is 20% complete
– dismantling of the floor slab formwork at level -6.6
– waterproofing works are 100% complete at level -3.3
– concreting of the floor slab on the 2nd floor is 100% complete
– knitting of the reinforcing frames of the vertical structures of the 3rd floor (columns, pylons, walls) continues


La Manche Clubhouse
Sections 4-5
– installation of ACP (aluminum composite) slopes around windows and balcony doors
– installation of brackets, then aluminum subsystems, and installation of porcelain stoneware tiles, installation of aluminum subsystem for fixing tiles
– installation of electrical cabinets (4th section)
– insulation with mineral wool in two layers (1st layer 10 cm, 2nd – 5 cm) 4 section – from 8th to 3rd floors
– installation of drainage plastic pipes for drainage from balconies (4th section)


Stanford
Section 101
– 135 m3 of brickwork was completed (internal and external walls)
Section 102
– facades on typical floors from the side of Ye. Konovalets Street have been completed
Section 108
– vertical elements of the 11th floor and the ceiling above it have been completed. All residential floors of this section have been completed. Further work on technical rooms and parapets on the roof will follow.
Section 110
– the floor slab of the -3rd floor has been completed
– work has begun on the erection of the vertical elements of the -2nd floor
Parking
– floor -5 floor slab completed
– 2 parking ramps completed
– floor -4 floor slab 70% complete
A total of 422 m³ of concrete was received per month.


Polaris Home&Plaza
Sections 4.1–3.3 – The engineering premises are ready for transfer for equipment installation.
Section 3.2 – The installation of window structures on the 24th floor has been completed and work has begun on the 25th.
Section 3.1 – Masonry of walls on the 10th and 11th floors continues.
Section 2.2 – Monolithic works: the installation of the floor slab above the 8th, 9th, 10th and 11th floors and the vertical elements of this level have been completed. Work has begun on the installation of the vertical elements of the 12th floor.
In total, 912.6 m3 of concrete was received at the site in one month.