Stanford RC
Section 101
- Installation of window structures is ongoing.
Section 102
- In progress: routing of heating and water supply systems across apartments and installation of floor screed.
- In the final stages: facade work on the inner courtyard side.
Section 103
- Routing of heating and water supply systems across apartments and installation of floor screed are ongoing.
- Insulation of parapets and ventilation shafts is underway.
Section 106
- Facade work on the basement floor facing the inner courtyard is nearing completion.
- In the final stages: installation of fire protection systems.
Section 109
- The monolithic structure of the 5th residential floor has been completed, and construction of the 6th-floor vertical elements is underway.
- 218.1 m³ of concrete were poured.
Parking
- The floor slab over the -2 floor has been completed, and work on the construction of the -1 floor is ongoing.
- 379.8 m³ of concrete were poured.


Apart-hotel VELMY
Block А
- Concreting of the 4th-floor slab has been completed.
- Vertical structures of the 5th floor are 40% complete.
- Setting up the horizontal shuttering for the 5th-floor slab is 25% complete.
- Laying of external and internal walls made of ceramic blocks on the 3rd floor is 100% complete.
- Laying of internal walls and partitions made of solid clay bricks on the 3rd floor is 25% complete.
- Installation of aluminum window and door units for the 1st-floor terrace access is 100% complete, and 10% complete on the 2nd floor.
Block В
- Vertical structures and concreting of the 3rd-floor slab have been completed.
- Vertical structures of the 4th floor are 45% complete.
- Setting up the horizontal shuttering for the 4th-floor slab is 20% complete.
- Laying of internal walls on the 1st floor has been completed.
Stylobate between blocks A and B
- Trimming of piles to the design horizontal level is 15% complete.
- Excavation and removal of soil from the transition tunnel between blocks A and B are 85% complete.
Phase 2
- Installation and tensioning of tieback anchors on the 1st tier of the retaining wall are 100% complete.
- Soil excavation and removal from the Block E pit are 5% complete.


La Manche Clubhouse
Section 4
- Technical flush-mount doors have been installed from the 2nd to the 8th floor; apartment doors from the 2nd to the 4th floor.
- Drilling of holes in the balcony concrete for waterproofing and rainwater drainage funnels is underway.
Section 5
- Apartment doors have been installed up to the 8th floor.
Section 3
- Installation of Gemafon from the 2nd to the 10th floor for the subsequent routing of water and heating supply networks is underway.
Section 2
- Installation of electrical grids in common areas for lighting has been completed.
Section 1
- Work has commenced on the installation of electrical grids in common areas.


Polaris Home&Plaza RC
Section 4.1
- Facade insulation has been completed — 110 m². Decorative plaster has been applied — 4,750 m². The facade has been painted — 700 m².
- Tiling of floors in common areas has been completed from the 3rd to the 11th floor.
- Work is ongoing on the installation of the decorative layer for walls and ceilings.
Section 3.3
- Facade insulation has been completed — 150 m². Facade reinforcement — 250 m². Application of decorative plaster — 450 m². Facade painting — 275 m².
- Plastering of common area walls from the 3rd to the 11th floor has been completed.
- Installation of apartment and technical doors from the 3rd to the 26th floor is 90% complete.
Section 3.2
- Facade insulation has been completed — 500 m². Facade reinforcement — 400 m². Application of decorative plaster — 700 m². Facade painting — 400 m².
- Plastering of common area walls from the 3rd to the 12th floor has been completed.
- Floor screed installation from the 18th to the 23rd floor has been carried out.
- Installation of heating and water supply pipes from the 3rd to the 18th floor is ongoing.
Section 3.1
- Brickwork of the 20th floor has been completed. Brickwork continues on the 14th, 15th, 17th, 21st, and 22nd floors. Work has commenced on the 23rd floor.
- Window installation from the 9th to the 13th floor has been completed.
Section 2.2
- Installation of the floor slab over the 21st floor and vertical structures of this level has been completed.
Section 2.1
- Vertical structures of the elevator and stair core on the 3rd floor are complete.
- Reinforcement of the elevator and stair core floor slab over the 3rd floor is 60% complete.
Parking
- Installation of the concrete bedding and monolithic foundation works have been completed.
In total, between May 1 and May 31, 2,429.5 m³ of concrete were poured at the site.


New Tone RC
Section 1.1
- The 3rd-floor floor slab and vertical structures are complete.
- Reinforcement of the 4th-floor floor slab has commenced.
Section 1.2
- 10 flights of stairs have been installed.
Section 2.3
- Reinforcement and concreting of basement walls and vertical structures are partially complete.
In addition, the arch covering for sections 1.1 – 2.3 has been completed. Over the past month, 264 m³ of concrete were poured at the site.